PRE-FEASIBILITY ENGINEERING
The 1st stage of any solar project is the Pre-Feasibility Analysis, where the customer analyses the solar potential at a given place, either on roof or on ground. The key findings from Pre-Feasibility Analysis are
​
-
Total Solar Capacity Estimation on the given roof / ground.
-
Presence of shading elements and net shading loss, impacting the input radiation.
-
Net energy estimation post the system losses.
-
An indicative solar panel layout and solar electrical SLD
-
Bill of materials for cost estimation.
​
With the above 5 documents from Valkan, the client and EPC company can include if the project is worthy for investment, and if it will be Techno - Commercially Feasible. ​
​
​
​
SITE SURVEY REPORT

Timeline:
-
Time Taken for Site visit : 2 to 3 days (Depending on the complexity of the site)
-
For submission of Site Visit Report: 2 days from Site Visit
-
Pre-Feasibility Engineering: 3 days from submission of Site Visit Report.